Largest SDS Component

The SDS water treatment plant is the largest and most complex project component. The seventh water treatment plant for Colorado Springs Utilities, the $125 million facility is scheduled to be finished in February 2016. The prime contracting team for the new water treatment plant is McCarthy Building Companies, Inc. and Carollo Engineers.

Design-Build Timeline

  • Design Phase:  Complete
  • Procurement phase: Complete
  • Construction phase: January 2013 – March 2016

Questions?

Kristin Kerr, Subcontractor Coordinator
Phone: (480) 449-4700(480) 449-4700; Email: kkerr@mccarthy.com

 
     

 

 


SDS Phase I

  • Pueblo Dam connection
  • Raw and finished water pipeline
  • 3 water pump stations
  • 1 water treatment plant
 