Permitting - Fountain Creek District Application

Fountain Creek District Application

The SDS project participants submitted an application to the Fountain Creek Watershed, Flood Control and Greenway District on Dec. 11, 2009, for approval of SDS-related construction activities in the Fountain Creek 100-year flood plain. On Jan. 22, 2010, the District Board voted unanimously in support of the SDS project components that fall within the Fountain Creek Corridor and recommended approval to the El Paso County Planning Commission for project facilities that are outside the Corridor but within the watershed in El Paso County.

Fountain Creek Application – Board Summary ( 3MB PDF)

Activities related to Fountain Creek District's review of the SDS Application:

January 2010
TAC approves recommending project to District Board
CAG approves recommending project to District Board
District Board review and approval January 22

December 2009
SDS presentation at Technical Advisory Committee (TAC) December 2
SDS presentation at Community Advisory Group (CAG) December 11
Application submitted December 11

SDS presentation delivered to TAC December 2 and CAG December 11. PDF Document.