Design: 40%
Land: 70% of properties secured
Focus: Constructing segment 1B, preparing a final design for segment 3 |
 |
|
| |
Design: 30%
Land: 100% of properties secured
Focus: Preparing a final design |
 |
|
| |
Design: 80%
Land: 40% of properties secured
Focus: Constructing segments 1A & 1B, preparing a final design for segments 1C & 2A, preparing a preliminary design for segment 2B |
 |
|
| |
Design: 30% design complete; completion of design planned in SDS Phase 2
Land: Acquisition planning under way
Focus: No significant activities |
 |
|
| |
Design: 30%
Land: Acquisition planning under way
Focus: Preparing a final design |
 |
|
| |
Design: 30%
Land: 100% of properties secured
Focus: Preparing a final design |
 |
|
| |
Design: 80%
Land: 90% of properties secured
Focus: Commencing construction of segment 1, constructing segments 2 & 3, preparing a final design for segment 4A, constructing segment 4B |
 |
|
| |
Design: 30%
Land: Coordinating land use authorization with the Bureau of Reclamation
Focus: Preparing a final design |
 |
|
| |
Design: 90%
Land: Not required
Focus: Constructing 1A, preparing a final design for 1B (pipeline) |
|
|
|