Current Project Status
report
Component
Schedule
Cost
Pipelines
stoplight stoplight
Raw Water Pump Stations
stoplight stoplight
Water Treatment Plant and Finished Pump Station
stoplight stoplight
archive
Legend
Schedule Status   Cost Status
stoplight
More than 30 days behind  
stoplight
More than 10% or $100K over
stoplight
Between 15 and 30 days behind  
stoplight
Between 0% and 10% over
stoplight
On schedule  
stoplight
On budget
hr
Click a Project Number on the map below or from the Project List to view additional project information.
   
9
 
Design: 40%
Land: 70% of properties secured
Focus: Constructing segment 1B, preparing a final design for segment 3
8
 
Design: 30%
Land: 100% of properties secured
Focus: Preparing a final design
7
 
Design: 80%
Land: 40% of properties secured
Focus: Constructing segments 1A & 1B, preparing a final design for segments 1C & 2A, preparing a preliminary design for segment 2B
6
Upper Williams Creek Reservoir
 
Design: 30% design complete; completion of design planned in SDS Phase 2
Land: Acquisition planning under way
Focus: No significant activities
5
 
Design: 30%
Land: Acquisition planning under way
Focus: Preparing a final design
4
 
Design: 30%
Land: 100% of properties secured
Focus: Preparing a final design
3
 
Design: 80%
Land: 90% of properties secured
Focus: Commencing construction of segment 1, constructing segments 2 & 3, preparing a final design for segment 4A, constructing segment 4B
2
 
Design: 30%
Land: Coordinating land use authorization with the Bureau of Reclamation
Focus: Preparing a final design
1
 
Design: 90%
Land: Not required
Focus: Constructing 1A, preparing a final design for 1B (pipeline)
Project Map